Category: Finances

  • 25.08.04 – Meeting Packet

    Ratify Prior Meeting Minutes – VOTE We need to ratify minutes from our prior meeting Litigation – Meet Our Lawyers! We have developments in our ongoing litigation related to the findings from our intrusive inspection. Our council is going to be attending the August 4th meeting to go over what we have so far, and…

  • 25.01.08 – Meeting Packet

    See Y’all at the meeting! Wednesday the 8th, 6pm. Meeting codes have already been emailed separately and will be taped to your door several times. If a quorum has not been met, the 2025 budget is automatically passed as per RCW 64.90.525.

  • 25.12.14 – Drainage / Tree Removal

    Drainage We have good progress on the 19732 drainage project! As of writing, the inspection has been completed and they have a scope of work that we have authorized them to move forward with, all within our target budget. The inspection work revealed our pump was overwhelmed with debris, and it was replaced @$950. The…

  • 24.12.02 – 2025 Budget

    Fence We have voted in favor of replacing the damaged fence posts near the mailboxes for $790 Budget We have finalized our 2025 budget. 8.88% increase; units ending in 01 = $721.43/mo, ending in 02 = $833.37/mo. 1x new roof, $15k for drainage work to rectify the faulty sump well protecting 19732. No basement storage…

  • 24.12.02 – Meeting Packet

    See Y’all at the meeting! Monday the 2nd, 6pm. Meeting codes have already been emailed separately and will be subtly taped to your door several times. This is the one to attend as we set our budget for 2025. NOTE: The above budget XLSX file is the framework we will be discussing, with formulas to…

  • 24.10.07 – Meeting Packet

    Roof Pictures Note these pictures span several days, at this point all but the gutters have been replaced, and we anticipate that being wrapped today or tomorrow. Basement Pictures All sheeting and misc debris cleaned and removed, all winter gear stored away, ready for reconstruction.

  • 24.01.24 – Association Update

    Winding down ‘Petty Cash’ With our previous management company we did not have the ability to operate bank cards within the bounds of their accounting. Thankfully Nash offers this capability; our reserve fund has been accounted for and drained into a cashiers check which Nash has confirmed receipt of. We are in the process of…

  • 23.11.10 – 2x Vendors on Monday

    Graffiti ‘Graffiti Busters’ will be onsite on Monday to address the tagging on 19732 Drainage As annual maintenance, ‘Best Plumbing’ will be onsite on Monday to jet the drain lines in the stairwells to the sump pump, and then clean out the sump pump well and its output line Gutters We are currently pursuing quotes…

  • 23.10.11 – Roof & Basement Update

    Roof at 19730 Current Condition: The roof of building 19730 has shown signs of deterioration, leading to water intrusion in unit 202. Immediate Action: Roofers are scheduled to tarp the building tomorrow. The primary goal is to stabilize the situation throughout the rainy season, deferring a full roof replacement to a drier period. Plan B:…

  • 23.07.16 – Weekly Update

    Annual Tasks Siding and gutters are being cleaned this week from Tuesday the 18th through Thursday the 20th. !!Close your windows!! I will be sticking reminders on everyone’s doors. You don’t want water getting into your AC intakes etc! Projects We have voted on a quote of $840.56 for the fascia board replacement and paint…